Mexico is moving from asking its largest energy users to report what they consume to requiring them to actively manage it. On September 30, 2026, the National Commission for the Efficient Use of Energy (CONUEE) published new general administrative provisions in the Federal Official Gazette (DOF). They cover the registration of High Energy-Consumption Pattern Users, known by the Spanish acronym UPAC, and the implementation of energy management systems. The rules took effect on October 1, 2026, replacing provisions in place since November 2018.
The legal basis is the Energy Planning and Transition Law (LPTE), published in March 2025, and its regulations issued in October 2025. These instructed CONUEE to set mandatory energy management requirements that take ISO 50001 into account. The most significant change is that registered facilities must now implement, and certify, an energy management system aligned with that international standard. Because the obligations apply facility by facility rather than company-wide, multinational groups need to review each Mexican site individually.
Who Qualifies as a UPAC
A person or company becomes a UPAC when any of its facilities in Mexico exceeded one of two thresholds during the previous calendar year: more than 45 GWh of electricity consumption, or more than 70,000 barrels of oil equivalent (boe) of fuel consumption, excluding energy used for transportation.
The electricity threshold is unchanged from the 2018 rules, but the fuel threshold has been lowered from 100,000 boe to 70,000 boe. This means more gas-intensive sites will now fall within scope, even if their electricity use is modest.
In practical terms, 45 GWh a year is equivalent to running about 5.1 MW of load continuously throughout the year. Using CONUEE’s 2026 conversion factors, 70,000 boe corresponds to roughly 11.3 million cubic meters of natural gas a year, or about 31,000 cubic meters a day. Facilities most likely to qualify include large vehicle assembly plants and factories that continuously operate foundries, hot forging, paint-drying ovens, heat-treatment furnaces or large boilers.
Companies cannot assume they will go unnoticed. CONUEE identifies UPACs both from the registry and from data submitted by third-party reporters, including electricity and fuel suppliers and marketers, which must also report annually.
What the Rules Require
Registration with CONUEE’s UPAC platform is mandatory, free, confidential and done online. Companies must sign up as soon as they know a site has passed a threshold, or within 15 business days of a notice from CONUEE. New registrants submit legal documents, the exact address of each site and its industry code under the NAICS classification used across North America.
Once registered, companies must report each year between March 1 and May 31, one month earlier than the previous June 30 deadline. For each facility, the report covers the previous year broken down by month, including:
- Energy consumed, by type of energy source
- Volume of goods or services produced
- Energy efficiency and decarbonization measures implemented, with their energy and economic results
- Progress in implementing the energy management system
The core new obligation is the energy management system itself. It must be based on the current ISO 50001 standard, or an equivalent Mexican Official Standard, and at a minimum must:
- Cover at least 80% of the facility’s total energy consumption
- Set objectives and targets based on an energy review no more than three years old
- Establish energy performance indicators and a continuous improvement program
- Apply operational and maintenance controls
- Maintain the documented information required by the standard
- Designate a person responsible for energy management at each facility, who acts as the contact with CONUEE
Companies that fail to comply, or that provide inaccurate or incomplete data, can face fines of between 100 and 1,000 times the daily value of the UMA, Mexico’s official reference unit for fines. Fines double for repeat offenses.

Key Deadlines and What Companies Should Do Now
The timeline is short. The main dates are:
- October 1, 2026: the provisions take effect
- March 1 to May 31, 2027: first annual reporting window under the new rules
- June 2027: CONUEE begins verifying energy management systems, including site visits and requests for information
- January 2028: facilities already identified as UPACs must hold ISO 50001 certification from a certification body accredited in Mexico
- New registrants have one calendar year from registration to obtain certification, with no extension
For most affected companies, this leaves around 15 months to move from reporting to a certified system. The first practical step is to screen consumption at each Mexican facility, including sites just below the thresholds, since a production increase could push them over. Companies should then check whether they can collect monthly energy and production data at the level of detail required, as this data underpins both the annual report and the performance indicators.
A gap assessment against ISO 50001 will show how much work remains, such as energy reviews, baselines and documented controls. Clear ownership also matters, with a named energy manager at each site and support from headquarters. Starting early is important, as demand for consultants and accredited auditors is likely to rise as the 2028 deadline approaches.
Conclusion
Mexico’s new UPAC provisions mark a shift from reporting energy use to managing it in a structured, verifiable way. A lower fuel threshold, an earlier reporting deadline, mandatory ISO 50001 certification by January 2028 and verification starting in June 2027 together raise the compliance bar for the country’s largest industrial energy users.
The requirements also bring benefits. The monthly data, performance indicators and improvement plans the rules demand are the same tools companies use to cut energy costs, reduce emissions and answer growing disclosure requests from customers and investors. Facilities that begin now can treat compliance as a foundation for better energy performance rather than a last-minute paperwork exercise.
Reference
- Hogan Lovells Cadwalader: Registration of high energy consumption users and implementation of Energy Management Systems